U.S. Orders Checks for Corrosion at Nuclear Reactors

March 26, 2002 

By MATTHEW L. WALD


 

WASHINGTON, March 25 - Nuclear reactor operators have been
ordered to check their reactor vessels after the discovery
that acid in cooling water had eaten a hole nearly all the
way through the six-inch-thick lid of a reactor at a plant
in Ohio. The corrosion left only a stainless-steel liner
less than a half-inch thick to hold in cooling water under
more than 2,200 pounds of pressure per square inch. 

At the 25-year-old Ohio plant, Davis-Besse, near Toledo,
the stainless steel was bent by the pressure and would have
broken if corrosion had continued, according to the Nuclear
Regulatory Commission, where officials were surprised by
the discovery. They said they had never seen so much
corrosion in a reactor vessel. 

The commission, which has warned plants for years to watch
for any corrosion, has ordered all 68 other plants of
similar design - pressurized-water reactors - to check
their lids. The commission is particularly worried about a
dozen of the oldest plants and ordered them to report by
early April whether they were safe enough to keep in
service. The commission told these plants to demonstrate
that technicians there would have noticed such corrosion in
their normal inspections, had it occurred. 

If the liner had given way in the Ohio reactor, experts
say, there would have been an immediate release of
thousands of gallons of slightly radioactive and extremely
hot water inside the reactor's containment building. 

The plants have pipe systems that are meant to pump water
back into a leaking vessel, but some experts fear that if
rushing steam and water damaged thermal insulation on top
of the vessel, the pipes could clog. In that event, the
reactor might have lost cooling water and suffered core
damage - possibly a meltdown - and a larger release of
radiation, at least inside the building. 

Such extensive corrosion "was never considered a credible
type of concern," said Brian W. Sheron, associate director
for project licensing and technology assessment at the
regulatory commission. 

Small leaks of cooling water are common, Mr. Sheron said,
but engineers always thought that if cooling water leaked
from the piping above the vessel and accumulated on the
vessel lid, the water would boil away in the heat of over
500 degrees, leaving the boric acid it contains in harmless
boron powder form. At Davis-Besse, however, it appears that
the water was held close to the metal vessel lid, or head,
perhaps by insulation on top of the vessel. 

Boric acid is used in cooling water to absorb surplus
neutrons, the subatomic particles that are released when an
atom is split and go on to split other atoms, sustaining
the chain reaction. 

Engineers are not yet certain why the corrosion occurred.


A nuclear engineer at the Union of Concerned Scientists, a
nonprofit watchdog group that is often critical of the
Nuclear Regulatory Commission, said the discovery was
troubling. 

"This is really something that shouldn't happen," said the
engineer, David Lochbaum. "You shouldn't get such a huge
hole in a pressure-retaining vessel." 

Edwin S. Lyman, the scientific director of the Nuclear
Control Institute, an anti-proliferation group based here,
said: "This is a pretty serious issue, and it has generic
implications. And it was discovered by accident." 

Workers stumbled on the problem in the process of fixing a
leaking tube that connects to the vessel head, which is 17
feet in diameter and weighs 150 tons. The tube is part of
the reactor control system; inside it there is a control
rod, which operators can lower into the core to smother the
flow of neutrons and stop the chain reaction, or raise to
allow the reactor to run. 

Technicians discovered that the metal that supports the
tube had mostly disappeared. 

The plant owner, FirstEnergy Corporation, is hoping to
patch the hole, an irregular opening about 4 by 5 inches.
But the commission is skeptical about whether this is
possible. 

No one in this country has replaced a reactor vessel head,
although several plants have ordered parts to do so.
FirstEnergy ordered a new head just before the extent of
the problem became obvious. A company spokesman said the
company hoped to install it in the spring of 2004. 

That date reflects how the industry, with no new reactor
orders in decades in this country, has limited production
capacity for such parts. 

The plant might also be able to use a vessel head from a
reactor in Midland, Mich., that was never completed, or
from a similar plant that was retired in 1989. 

Davis-Besse, which began operating in 1977, was not
designed with the idea that the head would be replaced;
technicians would have to cut a bigger hole in the
steel-reinforced concrete containment building to get the
new head into it. 

The company has not said what the job will cost, but Duke
Power Company, which operates three reactors similar to
Davis-Besse, plans to replace the heads of all three for
about $20 million. FirstEnergy could spend nearly that much
each month for electricity from alternative sources if it
must wait for the replacement part. 

Because of the discovery at Davis-Besse, the regulatory
commission ordered a dozen other plants to report back
within two weeks and prove that inspections they have done
in the past would have found any corrosion. 

The inspection cannot be done while the plant is running,
and if the utilities cannot convince the commission, they
presumably face shutdowns of perhaps several weeks just for
the checks. 

Such shutdowns occurred intermittently in the 1970's and
80's but have become extremely rare as reactors have
improved their reliability. 

The industry is hopeful, however, that inspections it began
under commission orders several years ago, to look for
leaks, would have found any similar cases. Those
inspections began after the heads of French reactors showed
signs of leaks and corrosion. 

"It could be something unique to Davis-Besse," said
Alexander Marion, director of engineering at the Nuclear
Energy Institute, the industry's trade association. A goal
for the investigation at the plant, he said, would be to
find out not only why the corrosion occurred but also why
it was not noticed sooner. 

"The plants are getting older and we're starting to see
these kinds of problems," Mr. Marion said. 

Copyright 2002 The New York Times Company