Report Finds Shortcomings In Energy Dept. Arms Testing

By Walter Pincus
Thursday, January 3, 2002; Page A15

The Energy Department's inspector general has determined that the growing
problems associated with the safety and reliability of the nation's nuclear
weapons, without nuclear testing, have become a "most serious challenge area"
for the newly established National Nuclear Security Agency that runs the
weapons complex.

In a report sent to Energy Secretary Spencer Abraham on Dec. 21 and made public
yesterday, Inspector General Gregory H. Friedman said one review his office
conducted last year turned up backlogs in flight and laboratory test schedules
for five of nine nuclear missile warheads and bombs in the operational
stockpile.

Another review, completed last month, showed backlogs of more than 18 months in
correcting defects or malfunctions that were discovered in testing of older
weapons systems.

"Without a robust and complete surveillance testing program, the department's
ability to assess the reliability of some nuclear weapons is at risk," Friedman
wrote.

Each year, the Pentagon and the Energy Department must certify to the president
that the nuclear weapons stockpile is safe and reliable and that there is no
need to resume tests involving the detonation of nuclear warheads and bombs in
underground caverns, as was done until 1992.

At a time when the Bush administration is contemplating sharp reductions in
offensive strategic nuclear missiles and bombs, some lawmakers and senior
officials inside the nuclear weapons complex and the Pentagon have been talking
about the need to resume underground testing, said Sen. John W. Warner (Va.),
ranking Republican on the Senate Armed Services Committee.

"If the surveillance program can't do the job, we will have to resume testing
to make sure our [nuclear] weapons work," Warner said recently.

The government's process of certifying "high confidence" in the nuclear
stockpile involves randomly selecting for testing about 11 units from each of
the nine deployed nuclear warheads on land- and submarine-based
intercontinental missiles and bombs on aircraft. Nuclear warheads, missiles and
bombs are flight-tested by being launched or dropped to see if the propellants
and guidance systems work.

The IG's report showed that, over the past four years, there were delays in
five of 16 tests scheduled for the W-80 warhead used on cruise missiles and in
three of 12 tests scheduled for the W-88, which is carried by the sub-launched
Trident II missiles.

Laboratory tests to see whether handling, aging or manufacturing problems have
developed in components such as radars showed delays in eight of 30 tests
related to the B-61 nuclear bombs and in eight of 31 tests planned for the W-76
warhead used on sub-launched Trident I missiles. Component tests -- which
include looking at "pits," or nuclear triggers and detonators -- are also
running behind, with four pit tests delayed out of 13 that were scheduled for
the four-year period.

When successful testing over four years falls below 75 percent of planned
tests, "there is significant concern that anomalies or defects in the stockpile
might have been missed," the IG's report said.

Part of the problem, according to the IG, is that the facilities of the nuclear
weapons complex have been aging and need increased spending for maintenance and
replacement. Congress recently approved an extra $200 million for such work,
but more is needed, Energy Department officials say.

When testing shows a defect or malfunction, department procedures require
immediate notification of the nuclear weapons lab that developed the weapon.
Five days after notification, the lab is supposed to determine whether the
problem is significant. If so, the lab has 45 days to determine through tests
whether a major investigation should be initiated since the reliability and
performance of the weapon could be involved.

About 10 percent of significant findings have resulted in "retrofits or major
design changes to the nuclear weapons stockpile," the IG reported.
Nevertheless, the IG recently found that the 45-day period for determining the
significance of problems had grown, in some instances, to 300 days.

After the determination had been made, "over two-thirds of the 64 active
investigations remained unresolved beyond the department's one-year benchmark
for completion," according to the IG's report.

Only a small cadre of engineers and experts carry out these investigations and
they often are involved in other projects, a former top Pentagon official said.
The IG noted that, as of March 2001, 18 of 24 such investigations remained
unresolved after 18 or more months at Los Alamos National Laboratory, which
spent the past two years adapting to tighter security rules in the wake of
allegations of Chinese espionage.

"If these delays continue, the department may not be in a position to
unconditionally certify the aging nuclear weapons stockpile," Friedman wrote.

© 2002 The Washington Post Company