the all-seeingeye 28' Sharpie: Building Log
Construction Diary

2003:

July 4 - 13

July 16 - 20

July 21 - 27

July 28 - Aug. 3

August 4 - 22

August 23 - 31

September

October

November
December

2004:

March

April

May

June

July

August

Rollover

September

October November

December

2005:

February

March

April

May

June-August

September

October

2006:

March

July-August

September

October

2007:

April-May

June

July

August

September

October

2008:

January

February

May

July

September

References Technical Notes Egrets and the Commodore

For the benefit of anyone contemplating a similar boat, here's the time and money being devoted to my "Egret"

That this project should be a time sink of enormous proportions is no surprise to me, as I have experience with a smaller stitch-and-tape project as well as a lot of general construction experience. I imagine a first-time builder setting out on a large project would be unpleasantly surprised by the investment of time it represents. When it's done, I'll divide the expenses out by hull, rig, tools, etc.

Running Total:

Hours Boat Expense (US$) Other Costs (US$)
527.75 8642.24 584.34

Itemized Expenses:

Date Subject Hours Expense (US$) Other Costs(US$)
July 4, 2003 Lumber trip, lofted molds, cut laminations for stem and stern. Molds for station 1-6 built 10.0 150.66
July 5, Finished molds, began set-up 4.0
July 6 & 7 Squared-up molds and began adding diagonals 2.75
July 9 Laminating stern pieces 1.0
July 10 Laminating stern and stern pieces 1.0
July 11 Porter-Cable Power Plane   197.58
July 11 Bevel stern assembly .50
July 12 Lofted deck beam curves, lumber trip 3.5 363.74
July 13 Molds completed, garage door closure built 8 37.83
July 14-15 Adjust molds, rip keelson sections 1.5
July 16 Rip chine/sheer stringer laminations, finish bevelling and set up stem lamination, secure first keelson section to stem. 3.5
July 17 Laminating keelson, cutting bending ducks 4.5
July 17 Ring shank boat nails   175.00

 
July 18-20 Laminating keelson, sheer stirngers. 17
July 22-23 Laminating sheer stringers, proof of concept test for mast hoop laminations, final version of mast hoop form built. 5.5
July 24 Laminating sheer stringers, ripping mast hoop stock for first run of hoops 2.0
July 25 Laminating sheer stringers, keelson, etc. 3.0 103.56
July 26-27 Sheer stringers completed, forward chine ends rabbetted, keelson finished. 13.0 152.30
July 28 Rabbet keeslon for chine stringers. Continue laminating chines forward. 3.0  
July 29 Continue laminating chines. 2.0  
July30- 31 Continue laminating chines, ripped mast hoop stock 5 547.42
August 1 Chines done, rabbetted for frames 9.0 150.87
August 2 Almost all frames cut and fit 11.0 698.99
August 3 Frames completed, test rigging block design 9.0  
August 4 Grind, sand, and epoxy prime framing 8.0  
August 5-7 Rough cut side panels, hang 2 after pre-soaking all in epoxy. Hang side panels and trim flush to chine stringer 17.0   44.20
August 8-12 Bottom panels cut and laid down, trimmed flush 14.0    
August 19 Lamination testing 1.0 30.66  
August 23 Sheave fabrication 2.0 13.57  
September 20- 28 Outer laminations 11.5 874.58 72.83
October 5-12 Outer laminations 16.0  
October 13-19 Outer hull laminations and trimming overhangs, replacing all temporary screws with final nails. Beginning to grind/fair hull. 10.5 101.50  
November 9 Yet more epoxy and cloth 503.50  
March 1-10, 2004 Fiddling about with blocks and learning a bit about sail sewing 3.0 276.98  
March 11-25 Fiddling about with blocks and learning a bit about sail sewing 6.0 84.09  
April 20 1840 pounds of lead bricks 97.52  
April 21-25 Finishing blocks, begin centerboard trunk 4.0 20.25  
May 1-3 Centerboard trunk 1.5  
May 3-10 Centerboard trunk 1.5  
May 16 Centerboard trunk 2.5  
May 22-23 Centerboard trunk-hang in place/mark for trimming 3.5  
May 28-29 Glassing centerboard trunk 2.5 89.00
June 12-13 Glassing centerboard trunk 4.0  
June 19-20 Hang trunk, first sheathing 8.5  
June 25-28 Hull taping, priming, grinding nail points, molds for deck and cabin beams 22.0  
July 13-18 Glassing hull and laminating beams 26.0 433.83 180.73
July 24-25 Sanding, filling, fairing, sanding deck beams 8.0  
July 26 Bronze Screws 150.01  
July 29 Epoxy and rollers, etc. 437.23  
July 30-31 Gelcoating, sanding 15.0  
August 8-9 Painting, build cradle 15.0  
August 7-9 Sledge bits, misc hardware 345.25  
August 12 Kirby paint 119.60  
August 12-13 Sledge bits, jack stands and tow ropes 169.20  
August 14-15 Rollover, trimming sheer clamps 20  
August 16 Trimming sheer clamps 2  
August 20-22 Trimming sheer clamps, installing deck beams 17  
September 4-6 Cutting floors, painting, cutting flotation 10  
September 6 Lumber and flotation   161.63  
September 11-12 Installing floors and first stern bulkheads 15 6.07  
September 13 Lumber   94.18  
September 18-19 Foward lazarette, deck carlins, main bulkhead 10    
September 20-30 Small bits and pieces 15    
October 1-18 Small bits and pieces 12 137.68  
October 23-30 Ceiling and interior trim 22 64.00  
December 22-26 Small bits and pieces 16 86.93  
February 5-20, 2005 Decking, CB lamination, interior work 26.5 773.22  
February 26-27, 2005 Centerboard, deck 10.5    
March 2-6, 2005 Centerboard and deck 11 346.39  
March 12-20, 2005 Decking, CB lamination, interior work 20    

Construction Diary

2003:

July 4 - 13

July 16 - 20

July 21 - 27

July 28 - Aug. 3

August 4 - 22

August 23 - 31

September

October

November
December

2004:

March

April

May

June

July

August

Rollover

September

October November

December

2005:

February

March

April

May

June-August

September

October

2006:

March

July-August

September

October

2007:

April-May

June

July

August

September

October

2008:

January

February

May

July

September

References Technical Notes Egrets and the Commodore